No. 19-917

Joslyn Manufacturing Company, LLC, et al. v. Valbruna Slater Steel Corporation, et al.

Lower Court: Seventh Circuit
Docketed: 2020-01-22
Status: Denied
Type: Paid
Experienced Counsel
Tags: cercla construction-threshold environmental-cleanup permanent-remedy remedial-action remedial-costs removal-costs statute-of-limitations
Key Terms:
Environmental SocialSecurity Privacy
Latest Conference: 2020-05-21
Question Presented (AI Summary)

Whether the six-year statute of limitations for 'remedial' work is triggered, as the court of appeals held below, only when the construction of a permanent solution for environmental contamination meets a threshold level of comprehensiveness

Question Presented (OCR Extract)

QUESTION PRESENTED The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), contains two different statutes of limitations for suits to recover environmental clean-up costs: (1) a three-year limitations period for suits to recover “removal” costs; and (2) a six-year period for suits to recover “remedial” costs. See 42 U.S.C. § 9613(g)(2)(A), (B). The three-year period to seek removal costs starts when the removal work is completed; the six-year period to seek remedial costs starts when physical on-site remedial construction begins. The terms “removal” and “remedial” are defined terms under CERCLA. See 42 U.S.C. § 9601(23), (24). “Removal” activity generally consists of clean-up measures taken in response to immediate threats to public health and safety; “remedial” activity means “actions consistent with [a] permanent remedy.” 42 U.S.C. § 9601(24). The question presented is: Whether the six-year statute of limitations for “remedial” work is triggered, as the court of appeals held below, only when the construction of a permanent solution for environmental contamination meets a threshold level of comprehensiveness. (i)

Docket Entries

2020-05-26
Petition DENIED.
2020-05-05
DISTRIBUTED for Conference of 5/21/2020.
2020-05-04
Reply of petitioners Joslyn Manufacturing Co., LLC and Joslyn Corp. filed. (Distributed)
2020-04-10
Motion to delay distribution of the petition for a writ certiorari granted. The petition will be distributed on the next distribution date after April 30, 2020, which is May 5, 2020.
2020-04-09
Motion of petitioner to delay distribution of the petition for a writ of certiorari under Rule 15.5 from April 22, 2020 to no earlier than April 30, 2020, submitted to The Clerk.
2020-04-05
Brief of respondents Valbruna Slater Steel Corp. and Fort Wayne Steel Corp. in opposition filed.
2020-03-16
Motion to extend the time to file a response is granted and the time is further extended to and including April 6, 2020.
2020-03-13
Motion to extend the time to file a response from March 23, 2020 to April 6, 2020, submitted to The Clerk.
2020-02-14
Motion to extend the time to file a response is granted and the time is extended to and including March 23, 2020.
2020-02-12
Motion to extend the time to file a response from February 21, 2020 to March 23, 2020, submitted to The Clerk.
2020-01-21
Petition for a writ of certiorari filed. (Response due February 21, 2020)
2019-11-27
Application (19A600) granted by Justice Kavanaugh extending the time to file until January 20, 2020.
2019-11-25
Application (19A600) to extend the time to file a petition for a writ of certiorari from December 5, 2019 to January 20, 2020, submitted to Justice Kavanaugh.

Attorneys

Joslyn Manufacturing Co., LLC and Joslyn Corp.
Carter G. PhillipsSidley Austin LLP, Petitioner
Valbruna Slater Steel Corp. and Fort Wayne Steel Corp.
David L. HatchettHatchett & Hauck LLP, Respondent